Timeline
MARCH
2017
Silent Phase Begins
Donors from the Pembroke Hill School community and Kansas City contributed over $44.5 million to support the Building Together campaign.
OCT. 25,
2019
Raider Rally
Pembroke Hill School students, parents, faculty, staff and alumni celebrated the beginning of the public phase of the Building Together campaign at an all-school rally, featuring a performance of the alma mater by a cross-campus choir assembled for the first time in Pembroke Hill history.
MAY 18,
2020
Construction Begins
Construction on the Ward Parkway Campus began with the demolition of the retaining wall that separates the upper and lower quad.
SUMMER
2020
Lawn and Site Work Begins
Ward Parkway Lawn and site work began along with first phase of the Hall Student Center parking lot configuration.
FALL
2020
Lawn Completed
Lawn completed with newly-placed sod and permanent sidewalks installed around the quad. Work went underway on changes to Hall Student Center and construction of Patterson Hall. Construction began on Bellis Athletic Center.
MARCH
2021
Lunch Served in Phillips Gym
After Spring Break, lunch was served to the Ward Parkway Campus community in Phillips Gym so that work could be completed in Hall Student Center.
AUGUST
2021
Patterson Hall Occupancy
Middle and upper school students, faculty and staff began to use Patterson Hall at the beginning of the 2021-22 school year.
DECEMBER
2021
Bellis Athletic Center Occupancy
Winter sports teams in the 2021-22 season were the first to use the Bellis Athletic Center.
JANUARY
2022
Pierson Gym Removal
Pierson Gym will be removed along with completion of the final, permanent phase of the Hall Student Center parking lot.